A pole stands vertically inside a scalene triangular park ABC. If the angle of elevation of the top of the pole from each corner of the park is same, then in ΔABC, the foot of the pole is at the
A marks her goods 25% above the cost price. She sells 25% of the goods at the marked price, 60% at 25% discount and the remaining at 10% discount. What is her overall gain or loss percent?
A completes 20% of a work in 5 days and B completes one-third of the work in 5 days. They began the work together but B leaves after 3 days. The total number of days needed for completion of the work is:
If 'A' is 7 times as efficient as 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together.